Title: Power Evacuation System Studies for Salalah Power Plant (IPP-2)
Start Date: 2013
End Date: 2014
Client: Dhofar Power Company (DPC)
Location: Oman
Scope Of Work: Detailed system study for finalization of proposed size of the plant, point of injection, the maximum unit size and additional transmission/substation requirement for the power evacuation.
Details:
As part of development of the Dhofar region, the Government of Oman has planned an independent power plant (IPP-2) in the Salalah area. The proposed IPP-2 will be rated in the range 300 - 400 MW and its power output shall be evacuated through DPC transmission network within the Salalah Power System (SPS). In view of the above, DPC is of the opinion that detailed system study is required for finalization of proposed size of the plant, point of injection, the maximum unit size and additional transmission/substation requirement for the power evacuation.