Master Plan of Power Distribution Network-Yazd MPPD


Title: Master Plan of Power Distribution Network-Yazd MPPD
Start Date: 2009
End Date: 2011
Client: YAZD Electrical Distribution Company
Main Client: YAZD Electrical Distribution Company
Location: Yazd-Iran
Scope Of Work: Scope Of Work:
 Load forecasting
 Load Modeling
 Distribution transformers placement
 Substation placement
 MV feeders routing and substation capacity expansion
 Short circuit analyzing protection devices coordination
 Network reliability assessment
 Capacitor placement
Details:
Project importance:
The fundamental purpose of distribution systems is the distribution of electric energy from transmission network to customers in the most cost-saving way. Systems should operate within thermal and voltage limits, at the same time taking care of reasonable level of an energy supply quality. In line with the approach to developing the electricity power distribution network into the adequate and reliable power distribution network, "Monenco Iran Consulting Engineers" have implemented the current project.
The objectives of Master Plan are:
• To identify requirements and prepare the investment plan related to distribution network modernization, including the revitalization or reconstruction of older facilities.
• To identify requirements and prepare the investment plan related to distribution network reinforcements.
• To prepare a list of components, equipment and materials for distribution development and rehabilitation, including cost estimate.
• To identify additional investments for rural electrification.