132kV portion successfully energized at existing A’salam Grid Station

132kV portion successfully energized at existing A’salam Grid Station

on Nov 15th, 132kV portion at existing A’salam Grid Station was successfully energized including:

  • 125MVA Transformer –  03rd & EAT-03 
  • 125MVA Transformer –  04th & EAT-04 

The scope of the project was to add 3rd and 4th Transformer - 132/33kV 125MVA – 2 Nos., 2 Numbers 500kVA EAT and 24 numbers 33kV GIS bays and 2 Nos 20 MVAR capacitor banks, 132kV cables and accessories and associated control panels.

During the commissioning phase of the project, the Client, OETC, appreciated Monenco performance in this project.