Construction of 63kv Cable Canal for Tehran Metro Company


Title: Construction of 63kv Cable Canal for Tehran Metro Company
Start Date: 2009
End Date: 2012
Client: Tehran Behro Railway Company Consultant Engineers
Main Client: Tehran Urban & Suburban Railway Company
Location: Tehran- Route through Metro substations
Scope Of Work: Scope Of Work:
Engineering services and supreme supervisory that include :
 Preparation of technical specification of tender documents
 Basic Design
 Detail Design
 Concept Design
 Contractors and proposals Evaluation
 Bid Evaluation & cooperation with Client for signing contract
 Site supervision

Details:
Project importance:
Due to Development of Tehran Subway Stations & Necessity of more Power Electrical Demand, These growth is Satisfied by Construction of new Substations & connecting them by Subtransmission Lines.
Because of Overhead Lines Right of way, Underground Cables are more useful in Central City Parts that here XLPE Cables will be used.